Western Isles development

Installation of Sevan FPSO mooring piles and ground chains

Home » Western Isles development

Scope of work

Project Comprised of the inshore loading (Lerwick, UK), offshore transport and offshore installation, including pre-tensioning, of the 12 mooring piles and chains at location.
Location Northern North Sea, UK Block 210/24a
Water depth 160 m
Client/Operator Subsea 7/Dana Petroleum
Award date
Installation date
Q1 2014
Q3 2014
SIMILAR PROJECTS

Load-out, transport and installation

The scope of work comprises the receipt, marshalling and preparation for installation of mooring components. Load-out, transport and installation of 24-off T-120 torpedo mooring pile and bottom chains. Components for Riser and Umbilical mooring system consisting of 11-off T- 35 torpedo mooring pile and bottom chains.

Phase 2

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.

Phase 3

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.

Technical data

Quantity / Size / Weight 12-leg mooring comprising of:
• 12 x 96” Driven Anchor Piles (152 t/ea)
• 12 x 210 m x Ø 159 mm Anchor Ground Chain

Equipment Resources

Installation Vessel

Key Equipment

HLCV Fairplayer and OCV Olympic Hera
• IHC S-800 Hydrohammer
• 96” ILT
• 72”- 96” Fast Frame
• 120 t Pull Chain Winch
• 2 x Work Class ROV
• Survey Spread
MORE ABOUT THE VESSEL
WANT TO KNOW MORE?
CONTACT US

SHARE THIS PROJECT

Related projects

COMPLETED IN 2021

Jumbo Yunlin Transport Scope

40 monopiles, 120 monopile sections and 40 transition pieces

Yunlin Offshore Wind Farm

Taiwan Strait, Taiwan

MORE INFO

COMPLETED IN 2021

Maximizing transport for DEME offshore

Monopile and transition piece transport, 37 voyages

Hornsea Two Offshore Wind Farm

North Sea

MORE INFO

COMPLETED IN 2018

The Arkona offshore wind farm project

Transportation and installation of the 60 transition pieces

385MW Offshore wind farm

German Baltic Sea

MORE INFO

DO YOU HAVE
ANY QUESTIONS?

Please contact our specialist
Close Menu