Turkey-Cyprus water supply
Transport and installation of subsea (crossing) suspension system
Scope of work
Project | Comprised of the project management, engineering, loadout & seafastening (port of Mersin Taşucu Seka, Turkey), transport to site, on-site survey and installation (incl. pre-tensioning) of 126 gravity anchors, tethers and buoys assemblies |
Location | Trans Mediterranean Water Pipe Crossing: Anamur (Turkey) – Geçitköy North Cyprus) |
Water depth | 280-1400 m |
Client/Operator | Turkish General Directorate of State Hydraulic Works |
Award date Installation date |
Q4 2013 Q2/Q4 2014 |
Load-out, transport and installation
The scope of work comprises the receipt, marshalling and preparation for installation of mooring components. Load-out, transport and installation of 24-off T-120 torpedo mooring pile and bottom chains. Components for Riser and Umbilical mooring system consisting of 11-off T- 35 torpedo mooring pile and bottom chains.
Phase 2
Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.
Phase 3
Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.
Technical data
Quantity / Size / Weight | 126 subsea anchor-tether-buoy assemblies: • Gravity Anchor: 9 m x 9 m x 2 m (200 t) • Tether: Ø 116 mm polyester rope • Buoy: Ø 3.7 m x 5.0 m (20t) |
Equipment Resources
Installation Vessel
Key Equipment |
HLCV Fairplayer • ROVs (200 hp Work Class) • Survey Spread • Tailor Made Lifting Gear |
WANT TO KNOW MORE?
Video highlights of the project
Related projects
COMPLETED IN 2021
Jumbo Yunlin Transport Scope
40 monopiles, 120 monopile sections and 40 transition pieces
Yunlin Offshore Wind Farm
Taiwan Strait, Taiwan
COMPLETED IN 2021
Maximizing transport for DEME offshore
Monopile and transition piece transport, 37 voyages
Hornsea Two Offshore Wind Farm
North Sea
COMPLETED IN 2018
The Arkona offshore wind farm project
Transportation and installation of the 60 transition pieces
385MW Offshore wind farm
German Baltic Sea
DO YOU HAVE
ANY QUESTIONS?
Please contact our specialist
Brian Boutkan
Manager Commerce Offshore
T: +31 (0)10 7900 300
M: +31 (0)6 11 92 66 10
E: b.boutkan@jumbomaritime.nl