TAQA subsea decom
Removal and disposal of subsea protection structures
Scope of work
Project | Comprises the subsea removal of three (3) subsea domes, previously used as wellhead protection structures, and the associated onshore disposal of the steel structures. Each subsea location will also be completed with mattress coverage of existing (in-situ) pipelines. |
Location | P/15 Field, The Netherlands |
Water depth | 26 m |
Client/Operator | TAQA Energy BV |
Award date Removal date |
Q1 2019 Q3 2019 |
Load-out, transport and installation
This project was part of a North Sea decommissioning program, where much of the offshore oil and gas infrastructure is reaching the end of its productive life and must be safely removed. A total of three subsea protection domes and piles at fields located in the P15 block, 35 kilometers off Hoek van Holland were removed, transported and disposed. Each dome had a dry weight of 150 tonnes
Technical data
Quantity / Size / Weight | Subsea Domes: • 14 m x 14 m x 6 m (120 t) |
Equipment Resources
Installation Vessel Key Equipment |
HLCV Fairplayer • Pile (Abbrasive) Internal Cutting Tool • ILT/Lift Frame • Mattress Lifting Frame |
WANT TO KNOW MORE?
Video highlights of the project
Related projects
COMPLETED IN 2021
Jumbo Yunlin Transport Scope
40 monopiles, 120 monopile sections and 40 transition pieces
Yunlin Offshore Wind Farm
Taiwan Strait, Taiwan
COMPLETED IN 2021
Maximizing transport for DEME offshore
Monopile and transition piece transport, 37 voyages
Hornsea Two Offshore Wind Farm
North Sea
COMPLETED IN 2018
The Arkona offshore wind farm project
Transportation and installation of the 60 transition pieces
385MW Offshore wind farm
German Baltic Sea
DO YOU HAVE
ANY QUESTIONS?
Please contact our specialist
Brian Boutkan
Manager Commerce Offshore
T: +31 (0)10 7900 300
M: +31 (0)6 11 92 66 10
E: b.boutkan@jumbomaritime.nl