Scope of work
Project | Pre-laying services for the anchoring system of FPSO (Guanabara), Flexible Lines and Umbilicals on the Mero 1 Project. |
Location | Brazil Santos Basin, North East area of Libra block. |
Water depth | 2000 m |
Client/Operator | Petróleo Brasileiro SA – Petrobras |
Installation date | Q2/Q3 2021 |
Load-out, transport and installation
The scope of work comprises the receipt, marshalling and preparation for installation of mooring components. Load-out, transport and installation of 24-off T-120 torpedo mooring pile and bottom chains. Components for Riser and Umbilical mooring system consisting of 11-off T- 35 torpedo mooring pile and bottom chains.
Phase 2
Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.
Phase 3
Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.
Technical data
Quantity / Size / Weight | 24-leg FPSO Mooring System comprising: • T-120 Torpedo Anchor Pile • Chain: Ø 120 mm x 615 m |
11 Flexible Riser and Umbilical Moorings comprising: • T-35 Torpedo Anchor Pile • Chain: Ø 76 mm x 30 m |
Equipment Resources
Installation Vessel Key Equipment | HLCV Fairplayer • Torpedo Pile overboarding frame (purpose-built) • Deployment winch • 2 x Work Class ROVs • Gypsy winch for chain handling |
Video highlights of the project
Related projects
COMPLETED IN 2021
Jumbo Yunlin Transport Scope
40 monopiles, 120 monopile sections and 40 transition pieces
Yunlin Offshore Wind Farm
Taiwan Strait, Taiwan
COMPLETED IN 2021
Maximizing transport for DEME offshore
Monopile and transition piece transport, 37 voyages
Hornsea Two Offshore Wind Farm
North Sea
COMPLETED IN 2018
The Arkona offshore wind farm project
Transportation and installation of the 60 transition pieces
385MW Offshore wind farm
German Baltic Sea
DO YOU HAVE
ANY QUESTIONS?
Please contact our specialist
Brian Boutkan
Manager Commerce Offshore
T: +31 (0)10 7900 300
M: +31 (0)6 11 92 66 10
E: b.boutkan@jumbomaritime.nl