OWF ARKONA Becken Südost
Installation of 60 transition piece foundations
Scope of work
Project | Comprised of the project management, engineering, inshore loading (Sassnitz), offshore transport and installation of 60 Transition Pieces onto pre-installed Mono Piles. Jumbo’s detailed scope also included the design and supply of all installation aids, lifting gear, grillages and sea fastenings. |
Location | Baltic Sea, German Waters |
Water depth | 23-37 m |
Client/Operator | Van Oord Offshore Wind Project / Eon |
Award date Installation date |
Q1 2017 Q4-2017 — Q1-2018 |
Jumbo completes project for the Arkona offshore wind farm
The entire project entailed the construction of a 385MW offshore wind farm in the German Baltic Sea. Jumbo was contracted by Van Oord for the installation of the 60 transition pieces. The vessel selected to undertake the task was the MV Fairplayer, a DP2 Heavy Lift Crane Vessel well-suited for the offshore demands of the Energy Industry worldwide.
Technical data
Quantity / Size / Weight | 60 Transition Pieces, each: • Height 18.0 m • Weight 290 t |
Equipment Resources
Installation Vessel
Key Equipment |
HLCV Fairplayer • Remotely controlled Hydraulic Lift Beam • Monopile Cleaning Spread • Motion Compensated Gangway (SMST) • Grouting Spread • Bolting Spread • Survey Spread |
WANT TO KNOW MORE?
Video highlights of the project
Related projects
COMPLETED IN 2021
Jumbo Yunlin Transport Scope
40 monopiles, 120 monopile sections and 40 transition pieces
Yunlin Offshore Wind Farm
Taiwan Strait, Taiwan
COMPLETED IN 2021
Maximizing transport for DEME offshore
Monopile and transition piece transport, 37 voyages
Hornsea Two Offshore Wind Farm
North Sea
COMPLETED IN 2018
The Arkona offshore wind farm project
Transportation and installation of the 60 transition pieces
385MW Offshore wind farm
German Baltic Sea