Pre-installation of deep water mooring and tie-in manifold

Home » Karish FPSO mooring installation

Scope of work

Project Comprises the Transport and Installation of the FPSO mooring system in 1760 m WD and the (near-shore) Tie-In Manifold in 70m WD.
Location Karish Gas Field, Israel
Water depth 70-1760 m
Client/Operator TechnipFMC / Energean Oil & Gas
Installation date Q2 2019/Q3 2020
SIMILAR PROJECTS
energean

Mooring system installed in 1,760m sea depth

The scope of work comprises the Transport and Installation of the FPSO mooring system in 1760 m WD and the (near-shore) Tie-In Manifold in 70m WD.

Jumbo Maritime installed the components on behalf of TechnipFMC at a depth of 1760 metres which was a new deep-water installation record.

Technical data

Quantity / Size / Weight FPSO Mooring System:
• Suction Anchor: Ø 9.0 m x 15 m (247 t)
• Suction Anchor: Ø 7.5 m x 15 m (187 t)
• Polyester Mooring Lines: Ø 195 mm x 3100 m

• Chains: Ø 127 mm x 200+149 m
Tie-In Manifold:

• TIM: 30 m 23 m x 15 m (609 t)

Equipment Resources

Installation Vessel

Key Equipment

HLCV Fairplayer
• 2x Work Class ROV
• SPT SAPS-008 Suction Spread
• Rope deployment Reel + RDS
• Chain Gypsy Winch
MORE ABOUT THE VESSEL
WANT TO KNOW MORE?
CONTACT US

SHARE THIS PROJECT

Video highlights of the project

Related projects

COMPLETED IN 2021

Jumbo Yunlin Transport Scope

40 monopiles, 120 monopile sections and 40 transition pieces

Yunlin Offshore Wind Farm

Taiwan Strait, Taiwan

MORE INFO

COMPLETED IN 2021

Maximizing transport for DEME offshore

Monopile and transition piece transport, 37 voyages

Hornsea Two Offshore Wind Farm

North Sea

MORE INFO

COMPLETED IN 2018

The Arkona offshore wind farm project

Transportation and installation of the 60 transition pieces

385MW Offshore wind farm

German Baltic Sea

MORE INFO

DO YOU HAVE
ANY QUESTIONS?

Please contact our specialist
Close Menu