REFINERY AND PETROCHEMICAL
Jumbo partners up with EMAS for mobilization lewek constellation
LEWEK CONSTELLATION | VIETNAM
16 March 2021 – Our Fairpartner was recently tasked to sail from the west to the east coast of India travelling almost 2600 nautical miles with three separate cargoes onboard, calling at five ports, all in 29 days. This is the longest time a Jumbo vessel has stayed in Indian waters and performed a complete coastal voyage.
06 March 2015
In 2014, Jumbo was awarded two contracts to mobilise various assets for EMAS’s flagship subsea construction vessel Lewek Constellation. The assets consist out of several reels and skidding drive materials, to be transported from Vung Tau (Vietnam) and Rotterdam (The Netherlands) to Pascagoula (USA). Several HLVs from Jumbo’s fleet were deployed to solve this logistic puzzle. Besides HLVs, Jumbo utilised various engineering solutions, operational know-how and project management skills creating added value for EMAS.
Logistics
In order to get the all the materials at the right place at the right time 4 HLVs were deployed:
- HLV Jumbo Javelin transported 4 reels
- HLV Fairpartner lifted 2 reels on to HLV Jumbo Vision for transportation
- HLV Fairlane transported skidding drive materials
Technical aspects loading reels on Jumbo Javelin
Both the cargo characteristics of the reels (832mt) as well as the local restrictions were taken into account. Restrictions like a shallow draft, limited space for upending of the reels and a short quay called for custom engineering solutions. To ensure safe operations, each of the lifting operations were thoroughly checked. Jumbo’s in-house 3d specialist created an animation for EMAS to demonstrate Jumbo’s engineering solution which involved a dual crane upending operation. All factors combined the Jumbo scope of work consisted out of the following steps:
- Upending of the reel(s)
- Positioning the reel into the cradle
- Lift combination of the cradle and reel onboard
In order to complete loading operations on the Jumbo Javelin, two spreader beams were specially designed and fabricated by Jumbo. The spreader beams allowed the Jumbo Javelin to load 4 reels with a single lift, where the original intake was limited to 2 reels only. The technical solution worked well and resulted in an efficient stowage. View the video for a detailed project overview.
Partnering up:
During the early stages of the project it was clear that a specific set of assets was needed to meet the detailed requirements. From the tendering phase onwards Jumbo partnered with EMAS to create the most efficient and safe solution. Jumbo’s project manager Boudewijn van der Garden states:
“I’m proud of the transportation solutions that we realized. It was great to work closely together with EMAS on technical challenges and realizing a maximum intake of HLV’s Jumbo Javelin and Jumbo Vision”.
Work relationships
Jumbo’s work relationship with EMAS started in July 2014. This long term project cooperation not only enabled transport from A to B but allowed Jumbo to think along with EMAS in designing a transport solution from A to Z. To realise this goal Jumbo took the entire project as well as the specific situation into account before the cargo was moved. Jumbo is grateful for the opportunity to work with EMAS again for the transportation of the last 2 reels in addition to the first 4 reels and skidding drive materials that are already in transport. After the reels are spooled in Pascagoula they will be taken into production on the new EMAS pipe laying vessel the Lewek Constellation.
Lewek Constellation
Lewek Constellation, the latest addition to the EMAS world-class fleet of pipelay and construction vessels, is designed to deliver complex projects in a safe, efficient and reliable manner in water depths exceeding 3,000 metres. For more information please consult www.emas.com.