ACC modules MV Svenja loading

By April 21, 2023No Comments
NEWS

Home » ACC modules MV Svenja loading

ACC modules MV Svenja loading

In 2021, Jumbo-SAL-Alliance was awarded a major project involving the transport of 27 Air Cool Condensers (ACC) modules, auxiliary modules, steam ducts, and staircases by CCZ JV (Chiyoda, CB&I, Zachry JV) for the Golden Pass LNG project.

A total of 215,529 freight tons, divided over nine shipments, had to be transported from Changshu, China, to Beaumont, USA, located in the Gulf of Mexico.

The heaviest ACC module weighed 260.4 mt and measured 25.91 x 14.44 x 17.32 meters. On 16.02.2023, our strong lady Svenja successfully discharged the cargo in Beaumont, USA.

I believe we won this project because of our solid technical solution and track record. The clearances were very tight, but we managed to stow all six units on deck.

Hiroshi WakabayashiGeneral Manager of Jumbo-SAL-Alliance Japan

Related news

NewsOffshoreSustainbility
October 4, 2023

Jumbo transports and installs Baltic Eagle Transition Pieces for Van Oord

Jumbo Offshore is fascinatingly dynamic. Besides its floating assets (the Heavy Lift Construction Vessels), the company’s core capabilities have been built on the skills of a committed team of experts.…
News
February 15, 2021

Jumbo’s innovative prototype

Jumbo's innovative prototype 15 February 2021 - Jumbo is pleased to present an in-house developed innovation that goes a long way to solve the issue of persistent flash rust caused…
Close Menu