NewsShipping

ACC modules MV Svenja loading

By April 21, 2023No Comments
NEWS

Home » ACC modules MV Svenja loading

ACC modules MV Svenja loading

In 2021, Jumbo-SAL-Alliance was awarded a major project involving the transport of 27 Air Cool Condensers (ACC) modules, auxiliary modules, steam ducts, and staircases by CCZ JV (Chiyoda, CB&I, Zachry JV) for the Golden Pass LNG project.

A total of 215,529 freight tons, divided over nine shipments, had to be transported from Changshu, China, to Beaumont, USA, located in the Gulf of Mexico.

The heaviest ACC module weighed 260.4 mt and measured 25.91 x 14.44 x 17.32 meters. On 16.02.2023, our strong lady Svenja successfully discharged the cargo in Beaumont, USA.

I believe we won this project because of our solid technical solution and track record. The clearances were very tight, but we managed to stow all six units on deck.

Hiroshi WakabayashiGeneral Manager of Jumbo-SAL-Alliance Japan

Related news

Arthur Hellinga, jumbo offshore, jumbo maritime, jumbo offshore contractors, Jumbo Offshore Insights #3NewsOffshoreJumbo Offshore Insights #3: The people behind the company Tender Management
June 5, 2023

Jumbo Offshore Insights #3: The people behind the company Tender Management

Jumbo Offshore is fascinatingly dynamic. Besides its floating assets (the Heavy Lift Construction Vessels), the company’s core capabilities have been built on the skills of a committed team of experts.…
Optimising Offshore Wind Foundation Installation, jumbo offshoreNewsOffshoreOptimising Offshore Wind Foundation Installation Through Multi-Contracting
March 2, 2026

Optimising Offshore Wind Foundation Installation Through Multi-Contracting

Jumbo Offshore is fascinatingly dynamic. Besides its floating assets (the Heavy Lift Construction Vessels), the company’s core capabilities have been built on the skills of a committed team of experts.…