ACC modules MV Svenja loading

In 2021, Jumbo-SAL-Alliance was awarded a major project involving the transport of 27 Air Cool Condensers (ACC) modules, auxiliary modules, steam ducts, and staircases by CCZ JV (Chiyoda, CB&I, Zachry JV) for the Golden Pass LNG project.

A total of 215,529 freight tons, divided over nine shipments, had to be transported from Changshu, China, to Beaumont, USA, located in the Gulf of Mexico.

The heaviest ACC module weighed 260.4 mt and measured 25.91 x 14.44 x 17.32 meters. On 16.02.2023, our strong lady Svenja successfully discharged the cargo in Beaumont, USA.

”I believe we won this project because of our solid technical solution and track record. The clearances were very tight, but we managed to stow all six units on deck.

Hiroshi WakabayashiGeneral Manager of Jumbo-SAL-Alliance Japan

Related news

NewsOffshoreJumbo Offshore completes TP T&I scope at Yunlin Offshore Wind Farm
September 5, 2024

Jumbo Offshore completes TP T&I scope at Yunlin Offshore Wind Farm

OFFSHORE INSTALLATION CONTRACTORS Jumbo Offshore completes TP T&I scope at Yunlin Offshore Wind Farm Jumbo Offshore has completed its TP (transition piece) T&I (transport & installation scope) on the Yunlin…
monopile removal works yunlinDecommissioningNewsOffshoreJumbo Offshore wraps up monopile removal works in Taiwan
June 6, 2024

Jumbo Offshore wraps up monopile removal works in Taiwan

PRESS RELEASE | 6 JUNE 2024 Jumbo Offshore wraps up monopile removal works in Taiwan Jumbo Offshore has completed the removal of two monopiles on the Offshore Wind Farm (OWF)…