ACC modules MV Svenja loading

In 2021, Jumbo-SAL-Alliance was awarded a major project involving the transport of 27 Air Cool Condensers (ACC) modules, auxiliary modules, steam ducts, and staircases by CCZ JV (Chiyoda, CB&I, Zachry JV) for the Golden Pass LNG project.

A total of 215,529 freight tons, divided over nine shipments, had to be transported from Changshu, China, to Beaumont, USA, located in the Gulf of Mexico.

The heaviest ACC module weighed 260.4 mt and measured 25.91 x 14.44 x 17.32 meters. On 16.02.2023, our strong lady Svenja successfully discharged the cargo in Beaumont, USA.

I believe we won this project because of our solid technical solution and track record. The clearances were very tight, but we managed to stow all six units on deck.

Hiroshi WakabayashiGeneral Manager of Jumbo-SAL-Alliance Japan

Related news

basrah project 7 voyagesNewsOil and gasShippingMV Svenja has commenced the first of seven voyages for JGC Corporation’s Basrah Refinery Upgrading Project.
May 15, 2023

MV Svenja has commenced the first of seven voyages for JGC Corporation’s Basrah Refinery Upgrading Project.

PROJECT UPDATE MV Svenja has commenced the first of seven voyages for JGC Corporation's Basrah Refinery Upgrading Project. On 7.05.2023, our good vessel MV Svenja, dedicated to the project for…
NewsPress ReleaseShippingJSI Alliance completes scope in Basrah Refinery Upgrading Project
April 11, 2024

JSI Alliance completes scope in Basrah Refinery Upgrading Project

PRESS RELEASE JSI Alliance completes scope in Basrah Refinery Upgrading Project On 11 March, MV Svenja discharged her cargo of 9 modules. The discharge marked the completion of the JSI…