Skip to main content
NewsShipping

ACC modules MV Svenja loading

By April 21, 2023No Comments
NEWS

Home » ACC modules MV Svenja loading

ACC modules MV Svenja loading

In 2021, Jumbo-SAL-Alliance was awarded a major project involving the transport of 27 Air Cool Condensers (ACC) modules, auxiliary modules, steam ducts, and staircases by CCZ JV (Chiyoda, CB&I, Zachry JV) for the Golden Pass LNG project.

A total of 215,529 freight tons, divided over nine shipments, had to be transported from Changshu, China, to Beaumont, USA, located in the Gulf of Mexico.

The heaviest ACC module weighed 260.4 mt and measured 25.91 x 14.44 x 17.32 meters. On 16.02.2023, our strong lady Svenja successfully discharged the cargo in Beaumont, USA.

I believe we won this project because of our solid technical solution and track record. The clearances were very tight, but we managed to stow all six units on deck.

Hiroshi WakabayashiGeneral Manager of Jumbo-SAL-Alliance Japan

Related news

News
July 6, 2022

Bigger and better at Breakbulk Europe 2022

NEWS | JUNE 2022 Bigger and better at Breakbulk Europe 2022 Thank you for joining us at Breakbulk Europe 2022! More than 9,045 people attended the 3-day project cargo and…
News
April 15, 2021

Jumbo shipping and SAL heavy lift launch Jumbo-SAL-Alliance

Jumbo shipping and SAL heavy lift launch Jumbo-SAL-Alliance Joint venture creates a new commercial heavy weight in project and breakbulk shipping with a fleet of 30 advanced heavy lift vessels.…
Close Menu