Free standing Hybrid Riser Buoyancy Can installation
Scope of work
Project | Transport and installation of five (5) Buoyancy Cans. At the field Technip connected together the individual components of the riser. The Fairplayer moved in for a wet handshake and at a depth of 160 m the 2,300 m long riser was taken over by the Fairplayer’s fore crane and placed in a hang-off frame for connection to the Buoyancy Can. The whole assembly was then over boarded, upended and lowered safely through the splash zone to a depth of 200m where it was de-ballasted by Technip. |
Location | Walker Ridge area, Gulf of Mexico, USA |
Water depth | 2500 m |
Client/Operator | TechnipFMC / Petrobras America |
Award date Installation date |
Q4 2008 Q4 2009 |
Load-out, transport and installation
The scope of work comprises the receipt, marshalling and preparation for installation of mooring components. Load-out, transport and installation of 24-off T-120 torpedo mooring pile and bottom chains. Components for Riser and Umbilical mooring system consisting of 11-off T- 35 torpedo mooring pile and bottom chains.
Phase 2
Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.
Phase 3
Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.
Technical data
Quantity / Size / Weight | Five (5) buoyancy cans: • Size 38 m x Ø 6.5 m • Weight: 350 t (module) / 780 t (full assembly |
Equipment Resources
Installation Vessel
Key Equipment |
HLCV Fairplayer • Deepwater Deployment System (first use) • Riser hang-off frame |
WANT TO KNOW MORE?
Video highlights of the project
Related projects
COMPLETED IN 2021
Jumbo Yunlin Transport Scope
40 monopiles, 120 monopile sections and 40 transition pieces
Yunlin Offshore Wind Farm
Taiwan Strait, Taiwan
COMPLETED IN 2021
Maximizing transport for DEME offshore
Monopile and transition piece transport, 37 voyages
Hornsea Two Offshore Wind Farm
North Sea
COMPLETED IN 2018
The Arkona offshore wind farm project
Transportation and installation of the 60 transition pieces
385MW Offshore wind farm
German Baltic Sea
DO YOU HAVE
ANY QUESTIONS?
Please contact our specialist
Brian Boutkan
Manager Commerce Offshore
T: +31 (0)10 7900 300
M: +31 (0)6 11 92 66 10
E: b.boutkan@jumbomaritime.nl