Turkey-Cyprus water supply

Transport and installation of subsea (crossing) suspension system

Home » Turkey-Cyprus water supplu

Scope of work

Project Comprised of the project management, engineering, loadout & seafastening (port of Mersin Taşucu Seka, Turkey), transport to site, on-site survey and installation (incl. pre-tensioning) of 126 gravity anchors, tethers and buoys assemblies
Location Trans Mediterranean Water Pipe Crossing: Anamur (Turkey) – Geçitköy
North Cyprus)
Water depth 280-1400 m
Client/Operator Turkish General Directorate of State Hydraulic Works
Award date
Installation date
Q4 2013
Q2/Q4 2014
SIMILAR PROJECTS

Load-out, transport and installation

The scope of work comprises the receipt, marshalling and preparation for installation of mooring components. Load-out, transport and installation of 24-off T-120 torpedo mooring pile and bottom chains. Components for Riser and Umbilical mooring system consisting of 11-off T- 35 torpedo mooring pile and bottom chains.

Phase 2

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.

Phase 3

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.

Technical data

Quantity / Size / Weight 126 subsea anchor-tether-buoy assemblies:
• Gravity Anchor: 9 m x 9 m x 2 m (200 t)
• Tether: Ø 116 mm polyester rope
• Buoy: Ø 3.7 m x 5.0 m (20t)

Equipment Resources

Installation Vessel

Key Equipment

HLCV Fairplayer
• ROVs (200 hp Work Class)
• Survey Spread
• Tailor Made Lifting Gear
MORE ABOUT THE VESSEL
WANT TO KNOW MORE?
CONTACT US

SHARE THIS PROJECT

Video highlights of the project

Related projects

COMPLETED IN 2021

Jumbo Yunlin Transport Scope

40 monopiles, 120 monopile sections and 40 transition pieces

Yunlin Offshore Wind Farm

Taiwan Strait, Taiwan

MORE INFO

COMPLETED IN 2021

Maximizing transport for DEME offshore

Monopile and transition piece transport, 37 voyages

Hornsea Two Offshore Wind Farm

North Sea

MORE INFO

COMPLETED IN 2018

The Arkona offshore wind farm project

Transportation and installation of the 60 transition pieces

385MW Offshore wind farm

German Baltic Sea

MORE INFO

DO YOU HAVE
ANY QUESTIONS?

Please contact our specialist
Close Menu