Alma and Galia field development

By March 17, 2023No Comments

Alma and Galia field development

FPSO tow-out, hook-up and installation

Home » Alma and Galia field development

Scope of work

Project The EnQuest Producer was towed from Port of Tyne to the field. At arrival in the field, the FPSO was positioned above the mooring and the chains were pulled and hooked into the FPSO. Once all mooring lines were connected, the chains were tensioned. Once in position the excess chain, rigging and installation aids were removed.
Location Central North Sea, UK Blocks 30/24, 30/25 & 30/29
Water depth 80 m
Client/Operator Enquest
Award date
Installation date
Q3 2012
Q2 2015
SIMILAR PROJECTS

Load-out, transport and installation

The scope of work comprises the receipt, marshalling and preparation for installation of mooring components. Load-out, transport and installation of 24-off T-120 torpedo mooring pile and bottom chains. Components for Riser and Umbilical mooring system consisting of 11-off T- 35 torpedo mooring pile and bottom chains.

Phase 2

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.

Phase 3

Lorem ipsum dolor sit amet, consectetur adipisicing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.

Technical data

Quantity / Size / Weight FPSO Tow-Out and Offshore Hook-Up:
• Tow from Newcastle (UK) to Field
• Hook-Up of Mooring Legs
• Diving Support

Equipment Resources

Installation Vessel

 

Key Equipment

• 1 off Command Anchor Hnadler (A-Frame)
• 3 off Heading Control Tugs (up to 200 t BP)
• 1 off DSV (EDT Protea)
• Tow gear
• Survey equipment and Navigation aids
• Work Class ROVs
MORE ABOUT THE VESSEL
WANT TO KNOW MORE?
CONTACT US

SHARE THIS PROJECT

Video highlights of the project

Related projects

COMPLETED IN 2021

Jumbo Yunlin Transport Scope

40 monopiles, 120 monopile sections and 40 transition pieces

Yunlin Offshore Wind Farm

Taiwan Strait, Taiwan

MORE INFO

COMPLETED IN 2021

Maximizing transport for DEME offshore

Monopile and transition piece transport, 37 voyages

Hornsea Two Offshore Wind Farm

North Sea

MORE INFO

COMPLETED IN 2018

The Arkona offshore wind farm project

Transportation and installation of the 60 transition pieces

385MW Offshore wind farm

German Baltic Sea

MORE INFO

DO YOU HAVE
ANY QUESTIONS?

Please contact our specialist
Close Menu