Pierce field lifetime extension
Replacement of Haewene BRIM FPSO mooring system
Scope of work
Project | Jumbo’s scope of work for this extremely short-track project consisted of the Transport and Installation of 8-off anchor piles including installation and pre-tensioning of 8-off bottom chain segments (200t tension at seabed). Finally, 5-off Spiral Strand Wires had to be connected to 5-off bottom chain segments and abandoned on the seabed. |
Location | Pierce Field, UK Block 23/22a and 23/27 |
Water depth | 86 m |
Client/Operator | Bluewater Energy Services / Shell |
Award date Installation date |
Q1 2016 Q2 2016 |
Replacement of Haewene Brim FPSO mooring system
As part of an ongoing program to extend the lifetime of the Bluewater-owned FPSO Haewene Brim, it was necessary to replace the existing mooring system. Jumbo was tasked with the Transport and Installation of 8 anchor piles sourced from Germany, which were to be driven into the seabed in the Pierce field (offshore Aberdeen).
This project involved not only the installation and pretensioning of 8 bottom chain segments, each with a tension of 200 tons at the seabed, but also the connection of 5 Spiral Strand Wires to 5 bottom chain segments, which were subsequently abandoned on the seabed.
Within a tight timeframe of 3 months from the contract award and while adhering to the given installation window, Jumbo successfully completed the offshore installation in a safe and efficient manner. Additionally, Jumbo designed and utilized a pile guide frame to ensure precise installation of the anchor piles according to the tolerances specified by the client.
Technical data
Quantity / Size / Weight | 8-leg FPSO Mooring System comprising of: • 8 x 84” 25,5 m Driven Anchor Piles • 1,290 m of Ø 147 mm Chain • 2,300 m of Ø 152 mm sheathed Spiral Strand Wire |
Equipment Resources
Installation Vessel
Key Equipment |
HLCV Fairplayer and OCV Olympic Zeus • Menck MHU-500T Hammer • ILT • Pile Guide Frame (purpose-built) • SSW Reel Drive System • 2 x Work Class ROVs • Gypsy Winch for chain handling |
WANT TO KNOW MORE?
Related projects
COMPLETED IN 2021
Jumbo Yunlin Transport Scope
40 monopiles, 120 monopile sections and 40 transition pieces
Yunlin Offshore Wind Farm
Taiwan Strait, Taiwan
COMPLETED IN 2021
Maximizing transport for DEME offshore
Monopile and transition piece transport, 37 voyages
Hornsea Two Offshore Wind Farm
North Sea
COMPLETED IN 2018
The Arkona offshore wind farm project
Transportation and installation of the 60 transition pieces
385MW Offshore wind farm
German Baltic Sea
DO YOU HAVE
ANY QUESTIONS?
Please contact our specialist
Brian Boutkan
Manager Commerce Offshore
T: +31 (0)10 7900 300
M: +31 (0)6 11 92 66 10
E: b.boutkan@jumbomaritime.nl