Scope of work

Project Comprised the load-out, transport and offshore installation of the FLNG soft yoke mooring system. Including pile driving, grouting and the installation of import riser and control umbilical.
Location Offshore Kribi, Cameroon
Water depth 19 m
Client/Operator Goler LNG / Perenco
Execution Q2-2017
SIMILAR PROJECTS

Load-out, transport and installation

he scope of work comprised the loaded-out, transported, and offshore installed the FLNG soft yoke mooring system. Including pile driving, grouting, and the installation of import riser and control umbilical.

For the Hilli Episeyo project, Jumbo provided a total T&I and hook-up solution, including pile driving, grouting, air-diving, and flex-lay services in a remote area in Cameroon. During the SSY pre-installation, Jumbo and its partner N-Sea performed DP2 air-diving works directly from the HLCV deck, thereby combining the heavy-lift solution with the subsea construction works.

Technical data

Quantity / Size / Weight NOV/APL Soft Yoke Mooring System:
• Anchor Base: 19 m x 17 m x 6m (251 t)
• Anchor Piles: Ø 96” x 36 m (94 t)
• Yoke Structure: 33 m x 33 m (704 t)
• Riser: 14” x 85 m (74 t)
• Control umbilical: 138 mm x 85 m (15 t)

Equipment Resources

Installation Vessel

Key Equipment

HLCV Fairplayer
• 550 kj hammer (Menck)
• 96” ILT (Menck)
• Air Dive Spread (N-Sea)
• Grout Spread (Foundocean)
• RDS
MORE ABOUT THE VESSEL
WANT TO KNOW MORE?
CONTACT US

SHARE THIS PROJECT

Video highlights of the project

Related projects

COMPLETED IN 2021

Jumbo Yunlin Transport Scope

40 monopiles, 120 monopile sections and 40 transition pieces

Yunlin Offshore Wind Farm

Taiwan Strait, Taiwan

MORE INFO

COMPLETED IN 2021

Maximizing transport for DEME offshore

Monopile and transition piece transport, 37 voyages

Hornsea Two Offshore Wind Farm

North Sea

MORE INFO

COMPLETED IN 2018

The Arkona offshore wind farm project

Transportation and installation of the 60 transition pieces

385MW Offshore wind farm

German Baltic Sea

MORE INFO